Abu Sultan Bridge,Egypt
A full clover leaf intersection lies on the highway road connecting Cairo and Ismailia in Egypt. A 2 roadway bridges are construted at the interchange of Fayed El Salheya road with Cairo – Ismailia desert road at 86 KM with a total length of 120m. The 2 middle spans are consist of pre-cast pre-stressed beams of 29.00m span supported on a V-shape archetictual columns. Above the middle column a special cast in-situ joint (6.00m long) is constructed to connect the pre-cast beams in order to decrease the beams depth (Continous system). The two edge spans are 22.00m each cast in-situ girder type bridge. The two separated bridge decks are 20.00m each. The loops are surface roads are 10.00m width, while the ramps are keystone walls with 10.00m width and with maximum height 10.00m
-
Contractor Consultant: SAAD INTERNATIONAL CONSULTANT ENGINEERS
-
Contractor: SAMCO
-
Scope of working: System idea, Final design & Site supervision
-
Date: 2015-2016
​
​
​